Davis Street Tree Removal The Week of July 22nd, 2024

Beginning Monday July 22nd,2024 - there will be a large amount trees removed on Davis St. The tree removal will be done by a contractor on the east side of Davis St from Reedy to Lick Creek. This work is part of the Davis St Phase II Project. The trees are being removed because the utilities need relocated further towards the edge of ROW as well as providing room for the future pedestrian pathways, bike lanes and stormwater improvements.